Inspection and Test Plans (ITP) in construction: what to include, with an example
An Inspection and Test Plan (ITP) sets out, before work starts, which inspections and tests will be carried out on a package, when, by whom, against what standard, and what record will prove it. It turns “we’ll check it” into a plan everyone can follow.
Why ITPs matter
- They catch defects before work is covered up, when fixing is cheap
- They make responsibilities clear between contractor, subcontractor and client
- They produce the records needed for handover, warranties, payment applications and, on higher-risk buildings, Gateway 3
What to include in an ITP
- Activity: the stage of work, such as set-out, installation or pre-close inspection
- Reference: the drawing, specification clause, standard or manufacturer’s instruction it’s checked against
- Acceptance criteria: what “right” looks like, ideally measurable (spacing, gaps, product, fixings)
- Inspection type: hold point, witness point or review
- Responsibility: who inspects (subcontractor, main contractor QA, client’s inspector)
- Frequency: every item, every floor or a sample
- Record: the form, checklist or test certificate that proves it, for example a Field View checklist with photos
Hold points, witness points and review points
- Hold point (H): work must stop until the inspection is done and accepted. Use these where work is about to be hidden.
- Witness point (W): the inspector is invited to attend, but work can continue if they don’t.
- Review point (R): documents are reviewed, such as product data or test certificates.
Example: fire stopping ITP (extract)
- 1. Product approval (R): fire strategy and spec checked; product data and installer competence approved before start. Record: approved submittal.
- 2. Services complete (H): M&E confirms all services through the wall are installed before sealing starts. Record: hand-back sign-off.
- 3. Installation (W): product, depth and annular gaps checked against manufacturer’s detail. Record: photo per penetration.
- 4. Labelling (H): each penetration labelled with ID, product, installer and date. Record: penetration register entry.
- 5. Pre-close inspection (H): QA inspects and accepts before boarding or ceilings. Record: Field View inspection with photos.
Step 2 is often missing. Our sample NCR shows what happens when services go in after the fire stopper has left.
Tips for ITPs that actually get used
- Keep them short: one page per package is usually enough
- Build them into the digital forms the site team already uses
- Agree hold points with the programme so inspections don’t cause delays
- Review pass rates monthly and tighten the ITP where defects repeat