Non-conformance report (NCR) (sample)

✓Construction QA

Non-Conformance Report

Fire stopping at service penetration · Riser 2, Level 4
NCR-016
Raised: 24 Feb 2026
Closed: 05 Mar 2026
SAMPLE REPORT · Fictional project, names, dates and results for illustration only

1. Details

ProjectResidential block, 32 apartments (fictional)
PackageFire stopping
LocationLevel 4 · Riser 2 · compartment wall grid C/4
SpecificationFire strategy rev D · Spec section K10 · Manufacturer’s installation guide
Raised byPeter Mindaugas Kvilis MCIOB (QA)
Responsible party[Fire stopping subcontractor]
CategoryMajor · life safety · hold point

2. Non-conformance

Two 110mm uPVC pipes and one cable tray pass through a 60-minute compartment wall with no fire stopping installed. Annular gap of 15–25mm around pipes. The area was due to be boarded on 26 Feb.

Photo 1

Unsealed penetrations, Riser 2

Photo 2

Annular gap measured ~25mm

Photo 3

Wall label: 60 min compartment

3. Immediate action

  • Hold point applied: no boarding of Riser 2 (L4) until NCR closed.
  • Location tagged on site and in Field View.

4. Root cause

M&E services were installed after the fire stopping visit for Level 4. There was no hand-back between trades, and the area was not flagged as open in the penetration register.

5. Corrective & preventive action

ActionOwnerDueStatus
Install intumescent pipe collars (110mm) and seal cable tray with approved system per manufacturer’s detailFire stopping sub03 MarDone
Label each penetration with ID, product, installer and dateFire stopping sub03 MarDone
Add “services complete → fire stopping” hand-back step to the Riser ITPQA / Main contractor05 MarDone
Toolbox talk on penetration sealing for M&E and fire stopping teamsSubcontractor supervisor05 MarDone

6. Re-inspection & close-out

Re-inspected05 Mar 2026 · collars and seal installed to manufacturer’s detail; labels present
Evidence6 photos, product data sheets, installer competence card (attached in Field View)
OutcomeClosed · hold point released for boarding
Raised by (QA)Peter Mindaugas Kvilis MCIOB · 24 Feb
Corrected by[Subcontractor supervisor] · 03 Mar
Accepted by[Main contractor] · 05 Mar
Construction QA, a trading name of Sapper Ltd · Company no. 09462720 · info@constructionqa.co.uk · 07468 944 222