Field View Snag Report
Pre-handover snagging · Flat 1.01 · Level 1
QA-SN-1.01
Snag walk: 02 Oct 2026
Re-inspected: 09 Oct 2026
Snag walk: 02 Oct 2026
Re-inspected: 09 Oct 2026
SAMPLE REPORT · Fictional project, names, dates and results for illustration only · structure based on real Field View snag exports
1. Scope
| Project | Residential block, 60 apartments (fictional) |
|---|---|
| Field View location | Project › Snagging › Block C › Level 1 › Flat 1.01 |
| Stage | Pre-handover snag walk, before client / warranty inspection |
| Task type | Snag · one task per defect, issued to the responsible trade package with photos |
| Snagged by | Inspector (Construction QA) with [Main contractor] site manager |
| Target | 7 days from issue for all trades |
2. Summary
20Snags raised
14Closed at re-inspection
4Work completed – to check
2Still open
3. Snags by trade
| Trade package | Raised | Closed | Open / to check | Progress |
|---|---|---|---|---|
| M&E (electrical & ventilation) | 5 | 3 | 2 | |
| Painting & decorating | 6 | 4 | 2 | |
| Sealants (mastic) | 4 | 3 | 1 | |
| Cleaning | 2 | 2 | 0 | |
| Drylining (metal stud & board) | 1 | 0 | 1 | |
| 2nd fix carpentry | 2 | 2 | 0 | |
| Total | 20 | 14 | 6 |
4. Snag register
| # | Ref | Room | Snag | Trade | Photos | Status 09 Oct |
|---|---|---|---|---|---|---|
| 1 | S-004 | Living | Back boxes to be fixed; TV/data faceplates missing | M&E | 1 | Closed |
| 2 | S-005 | Hall | Faceplates missing; thermostat not clipped home | M&E | 1 | Closed |
| 3 | S-006 | Bathroom | Extract fan not installed / not connected | M&E | 0 | Open |
| 4 | S-007 | Bedroom | Downlight bezel missing | M&E | 1 | Closed |
| 5 | S-008 | Living | Dimmer switch knobs not fitted | M&E | 1 | To check |
| 6 | S-009 | Throughout | Touch-up and redecorate marks, scuffs and scratches | Decorating | 14 | To check |
| 7 | S-010 | Throughout | Caulk around sockets, door frames and skirtings; repaint | Decorating | 7 | Closed |
| 8 | S-011 | Bedroom | Sealant to window board / reveal incomplete | Sealants | 2 | Closed |
| 9 | S-012 | Bedroom | Sealant around wardrobe missing | Sealants | 1 | Closed |
| 10 | S-013 | Balcony | Clean balcony door and handle | Cleaning | 2 | Closed |
| 11 | S-014 | Bedroom | Poor joint finish at window reveal – sealant looks untidy | Drylining | 1 | Open |
| 12 | S-015 | Hall | Fill gouge in door edge and repaint | Decorating | 1 | Closed |
| 13 | S-016 | Hall | Architrave mitre joint open – tidy | Carpentry | 1 | Closed |
| 14 | S-017 | Bathroom | Fill and paint wall damage | Decorating | 5 | Closed |
| 15 | S-018 | Bathroom | Seal vanity unit after making good | Sealants | 1 | To check |
| 16 | S-019 | Hall | Decorate inside small cupboard | Decorating | 4 | To check |
| 17 | S-020 | Utility | Caulk gap inside utility cupboard | Decorating | 1 | Closed |
| 18 | S-021 | Utility | Clean utility cupboard | Cleaning | 3 | Closed |
| 19 | S-022 | Utility | Skirting not installed | Carpentry | 1 | Closed |
| 20 | S-023 | Utility | Seal around boiler feet for a neat finish | Sealants | 1 | Closed |
5. Typical snag evidence

S-014 · Joint finish at reveal checked

S-016 · Architrave joint re-checked

Snag walk against the room schedule
6. Actions
| Action | Owner | Due |
|---|---|---|
| Install and commission bathroom extract fan (S-006) – needed for handover | M&E | 13 Oct |
| Rework joint at window reveal before sealant is redone (S-014) | Drylining → Sealants | 14 Oct |
| Check 4 snags marked Work completed at the next visit | QA | 14 Oct |
| Flat 1.01 ready for client inspection once all 20 snags are closed; export the closed list for the handover file | Main contractor / QA | 16 Oct |
Snagged byInspector · QA (outsourced)
With[Main contractor site manager]
Data sourceField View snag export, Flat 1.01