Gateway 3 · QA Evidence Gap Analysis
Higher-risk building · 19-storey student accommodation, 640 beds
G3-GA-01
Rev A
Data date: 20 Feb 2026
Rev A
Data date: 20 Feb 2026
SAMPLE REPORT · Fictional project, names, dates and results for illustration only
1. Scope
| Building | 19 storeys, 58m, purpose-built student accommodation |
|---|---|
| Status | Higher-risk building (Building Safety Act 2022) |
| Principal Contractor | [Principal Contractor] |
| Target completion | Q3 2026 · Gateway 3 application planned 10 weeks before |
| Review | Field View records, ITPs, test certificates, O&M drafts, sample site verification on L3, L9, L16 |
| Reviewer | Peter Mindaugas Kvilis MCIOB |
12Safety-critical elements
71%Evidence complete
3Red elements
41Actions raised
Key finding: Evidence is strong for structure, sprinklers and smoke control. Fire stopping, cavity barriers and fire doors have gaps that can still be closed while areas are accessible. Waiting until commissioning would risk opening up finished work and delaying the application.
2. Evidence status by element
| Element | Evidence required | Available | Status | Complete |
|---|---|---|---|---|
| Structural frame | Pour records, cube results, engineer sign-off | All floors | Green | |
| Compartmentation walls | ITPs, pre-close inspections, photos per wall | L1–L14 only | Amber | |
| Fire stopping (penetrations) | Per-penetration record, product data, installer certs | ~55% of penetrations | Red | |
| Cavity barriers (façade) | Location plan, install photos before closing, inspection | No photos L10–L13 | Red | |
| Façade system | Fixing inspections, product certs, test evidence | Complete to L17 | Amber | |
| Fire doorsets | Certification, install inspection, gap checks | Install checks 40% | Red | |
| Sprinklers | Install, pressure tests, commissioning plan | Tests to L18 | Green | |
| Smoke control | Install records, commissioning plan | Complete to date | Green | |
| Dry riser | Install, pressure test | Test L1–L19 | Green | |
| Fire alarm & detection | Install, cause & effect, commissioning | Install 80% | Amber | |
| Firefighting lift | Install, test plan | In progress | Amber | |
| As-built information (golden thread) | Linked drawings, change log, O&M | Structure agreed, partly populated | Amber |
3. Priority actions
| # | Action | Owner | Due | Priority |
|---|---|---|---|---|
| 1 | Survey and record all open penetrations L10–L19 before ceiling close-up; one record per penetration in Field View | Fire stopping sub + QA | 27 Mar | High |
| 2 | Cavity barriers L10–L13: intrusive sample inspection (min. 10 locations) to confirm installation; record findings | Façade sub + QA | 13 Mar | High |
| 3 | Fire doorsets: complete install inspections incl. gaps, hinges, seals; link certification to door schedule | Joinery sub + QA | 10 Apr | High |
| 4 | Compartmentation L15–L19: pre-close inspections at hold points before boarding | Drylining sub + QA | Ongoing | Medium |
| 5 | Golden thread: agree folder structure and naming; link each record to location and drawing revision | Principal Contractor | 20 Mar | Medium |
| 6 | Fire alarm cause & effect sign-off with commissioning programme | M&E contractor | 24 Apr | Medium |
4. Sample verification on site
| Floor | Items checked | Matched records | Comment |
|---|---|---|---|
| Level 3 | 24 | 23 | 1 penetration sealed but no record → recorded |
| Level 9 | 24 | 21 | 3 penetrations with no record; 1 incorrect product (NCR raised) |
| Level 16 | 18 | 12 | Records not yet uploaded by subcontractor |
5. Recommendation
Set a 12-week evidence recovery plan with weekly reporting against the actions above, and make closed-up areas conditional on a completed Field View record. Re-run this analysis at Rev B (target 22 May 2026) to confirm readiness for the Gateway 3 application.
Prepared byPeter Mindaugas Kvilis MCIOB
For[Principal Contractor] · Building Safety Manager
NoteQA evidence review only. Statutory sign-off rests with the Principal Contractor and the Building Safety Regulator.