Monthly QA Report · Field View
Drylining & fire stopping package · 32-unit residential block, 6 storeys
QA-M-04
Period: Feb 2026
Issue 1
Period: Feb 2026
Issue 1
SAMPLE REPORT · Fictional project, names, dates and results for illustration only
1. Summary
| Project | Residential block, 32 apartments, ground + 5 floors |
|---|---|
| Package | Drylining, partitions & fire stopping |
| Main contractor | [Main contractor] |
| Subcontractor | [Drylining subcontractor] |
| QA platform | Field View (main contractor project) |
| Site visits this month | 8 called-in visits at hold points · no full-time QA on site |
46Inspections completed
85%First-time pass rate
7NCRs raised
4NCRs closed
Headline: Levels 1–3 drylining ITPs complete. First-time pass rate up from 78% in January. Main risk: fire stopping at service penetrations on Level 4 (3 NCRs open). Recommend a toolbox talk for the M&E and fire stopping teams before Level 5 starts.
2. Inspections by type
| Inspection (Field View form) | Done | Pass | Fail | Pass rate |
|---|---|---|---|---|
| Metal stud framing & set-out | 12 | 11 | 1 | 92% |
| Board fixing (pre-tape) | 10 | 9 | 1 | 90% |
| Acoustic insulation | 8 | 8 | 0 | 100% |
| Fire-rated partitions (pre-close) | 6 | 4 | 2 | 67% |
| Fire stopping at penetrations | 10 | 7 | 3 | 70% |
| Total | 46 | 39 | 7 | 85% |
3. ITP progress by floor
| Floor | Framing | Boarding | Fire stopping | Overall |
|---|---|---|---|---|
| Level 1 | Complete | Complete | Complete | |
| Level 2 | Complete | Complete | Complete | |
| Level 3 | Complete | Complete | In progress | |
| Level 4 | Complete | In progress | 3 NCRs | |
| Level 5 | In progress | Not started | Not started |
4. NCR register (this period)
| NCR | Location | Description | Status | Target |
|---|---|---|---|---|
| NCR-014 | L3 · Flat 3.04 | Board joints not staggered at fire-rated wall | Closed | — |
| NCR-015 | L3 · Corridor | Deflection head missing intumescent strip | Closed | — |
| NCR-016 | L4 · Riser 2 | Unsealed pipe penetration through compartment wall | Open | 06 Mar |
| NCR-017 | L4 · Riser 2 | Wrong collar size on 110mm soil pipe | Open | 06 Mar |
| NCR-018 | L4 · Flat 4.06 | Gap >10mm at partition/slab junction | Open | 09 Mar |
| NCR-019 | L2 · Flat 2.01 | Stud spacing 650mm (spec 600mm) | Closed | — |
| NCR-020 | L4 · Flat 4.02 | Cable bundle through fire wall not sealed | Closed | — |
5. Photo evidence (from Field View)
Photo 1
NCR-016 · unsealed penetration, Riser 2
Photo 2
NCR-017 · collar size check
Photo 3
NCR-015 closed · intumescent strip fitted
6. Actions for next period
| Action | Owner | Due |
|---|---|---|
| Close NCR-016/017/018 and re-inspect before boarding Riser 2 | Subcontractor / QA | 09 Mar |
| Toolbox talk: penetration sealing to manufacturer’s details | Subcontractor supervisor | 05 Mar |
| Issue Level 3 fire stopping evidence pack to main contractor | QA | 13 Mar |
| Attach this report and Level 1–3 inspection records to Application for Payment No. 7 as evidence of completed, accepted work | Subcontractor QS | 25 Mar |
| Add closed Level 1–3 records to the golden thread quality package | QA | 31 Mar |
Prepared byPeter Mindaugas Kvilis MCIOB
QA Manager (outsourced)
QA Manager (outsourced)
Reviewed by[Main contractor QA lead]
Data sourceField View export, 01–28 Feb 2026